PSK-I Part F: Flow Metrics & Forecasting
Certifications

PSK-I Part F: Flow Metrics & Forecasting

This is Part F of the PSK-I Exam Prep series. It is the longest section โ€” flow metrics and forecasting are heavily tested and reward deep understanding over surface familiarity.


F0. The Four Flow Metrics โ€” Overview

These are the only four flow metrics in the Kanban Guide. Velocity and story points are not among them.

MetricApplies toOne-line meaning
WIPIn-progressItems started but not finished
Cycle TimeFinishedElapsed time: start โ†’ finish
Work Item AgeIn-progressElapsed time since started (so far)
ThroughputFinishedItems finished per unit of time

The two key pairings.

  • Cycle Time (finished) vs Work Item Age (in-progress) โ€” same clock, different population.
  • Throughput (raw count) vs velocity (size-weighted) โ€” throughput ignores item size.

How questions come.

  • “Which is NOT one of the four flow metrics?” โ†’ velocity / story points.
  • “Which two are flow metrics?” (multi) โ†’ any two of WIP, Cycle Time, Work Item Age, Throughput.

F1. Work in Progress (WIP)

What it is. The number of work items started but not finished, per the DoW.

Provides transparency into load; visualised as the band height on a CFD or a WIP-over-time chart. Don’t confuse the metric (a count) with the limit (a policy). WIP just reports; the WIP limit constrains.

Worked example. A board shows 9 items between “In Progress” and “Review.” WIP = 9. If the WIP limit across those states is 6, the metric tells the team they’re over their policy and should finish before starting more.

How questions come.

  • “WIP is defined asโ€ฆ” โ†’ items started but not finished.
  • “Most useful metrics in the Daily Scrum?” โ†’ WIP + Work Item Age.

F2. Cycle Time

What it is. The elapsed time from when an item starts to when it finishes โ€” measured on completed items only.

Important characteristics.

  • A lagging indicator โ€” known only after an item finishes.
  • Used to understand turnaround, set expectations, and (via percentiles) define the SLE.
  • Measured from the team’s defined “started” point (per DoW) to “finished” โ€” not from initial idea.

Misconception to avoid. “Cycle Time tells me about work in progress.” It can’t โ€” it’s only known after finishing. For in-progress risk, use Work Item Age.

Worked example. An item started June 1 and finished June 6 โ†’ Cycle Time = 5 days. Plotting 100 such items, the 85th-percentile line sits at 8 days โ†’ that becomes the SLE.

How questions come.

  • “When is Cycle Time known?” โ†’ only after the item finishes (lagging).
  • “Cycle Time vs Work Item Age?” โ†’ Cycle Time = finished items; Age = in-progress items.

F3. Work Item Age

What it is. The elapsed time since an in-progress item started, up to now.

The live counterpart to Cycle Time. Because it’s available while work is in progress, it’s the best metric for predicting when a started item will finish and for flagging risk. Compare an item’s age to the SLE and its position in the workflow.

Key nuance. Age alone isn’t “bad.” A 10-day-old item near “Done” may be fine; the same age near “Start” is a red flag. Read age together with workflow position.

Misconception to avoid. “Use Cycle Time to spot at-risk work.” Too late โ€” Cycle Time is only known after finishing. Work Item Age is the in-flight signal.

Worked example. At the Daily Scrum, an item is 6 days old against an 8-day SLE and still mid-workflow. The team acts now โ€” swarms it โ€” to finish before it breaches, rather than waiting.

How questions come.

  • “Which metric best predicts when a started item will finish / which item is most at risk?” โ†’ Work Item Age (vs the SLE).
  • “Most useful in the Daily Scrum?” โ†’ Work Item Age + current WIP.

F4. Throughput

What it is. The number of work items finished per unit of time (day/week/Sprint).

A raw count at the finish line โ€” no compensation for item size. That’s the crucial difference from velocity, which weights by estimate/story points. Throughput drives “how much / by when” forecasting.

Misconception to avoid. “Throughput = velocity.” No โ€” velocity is size-weighted; throughput is a plain count. Because throughput ignores size, it’s most reliable when items are broken down to be small and similar.

Worked example. Last six weeks the team finished 4, 5, 3, 6, 5, 4 items (avg โ‰ˆ 4.5/week). For a two-week Sprint they plan capacity around ~9 items and feed the same history into a Monte Carlo for a probabilistic forecast.

How questions come.

  • “How does Throughput differ from velocity?” โ†’ it counts finished items with no size compensation.
  • “Which metric informs capacity / ‘how many by when’?” โ†’ Throughput.

F5. Little’s Law

Practical statement (flow form):

Average Cycle Time โ‰ˆ Average WIP รท Average Throughput

Plain-English meaning. For a given throughput, the more items in progress at once, the longer each takes on average. If cycle times are too long, the first lever is to lower WIP.

Rearrangements for calculation questions.

GivenSolve forFormula
WIP + ThroughputCycle TimeWIP รท Throughput
WIP + Cycle TimeThroughputWIP รท Cycle Time
Cycle Time + ThroughputWIPCycle Time ร— Throughput

Worked calculations.

ScenarioAnswer
WIP 10, Throughput 2/day โ†’ Cycle Time?5 days
WIP 15, Cycle Time 5 days โ†’ Throughput?3/day
Cycle Time 4 days, Throughput 3/day โ†’ WIP?12
Throughput 5/week, 20 items โ†’ time?4 weeks

Quick check. WIP 12, Throughput 3/day โ†’ Cycle Time = 4 days. 18 items at 6/week โ†’ 3 weeks.

Misconception to avoid. “Add WIP to raise throughput.” No โ€” it lengthens cycle time without raising throughput.

How questions come.

  • Calculation: given two of {WIP, Cycle Time, Throughput}, solve for the third.
  • “Reducing WIP, throughput steady, does what to cycle time?” โ†’ reduces it.
  • “Cycle times are too long โ€” first action?” โ†’ lower WIP.

F6. The Four Charts

The exam asks you to read charts, match a metric to the right chart, or diagnose a flow problem. Know each chart’s axes, what it’s best at, and its failure signature.

Cycle Time Scatterplot

Axes. x = date item finished; y = its cycle time (days).

What it shows. Every finished item as a single dot. Horizontal percentile lines (50th, 85th, 95th) summarise the distribution.

How to read it.

  • Low, tight cloud = fast and predictable flow.
  • Tall, scattered cloud = high variability (low predictability), even if the average looks fine.
  • High outliers = individual items that took unusually long โ€” candidates to inspect in the Retrospective.
  • The 85th-percentile line is where you read the SLE.

Worked example. 100 finished items; the 85th-percentile line sits at 8 days. Read: “85% of our items finish within 8 days.” That is the SLE. If a stakeholder wants more certainty, quote the 95th line (a longer number, e.g. 13 days) โ€” higher confidence always means a longer time.

How questions come.

  • “Which chart is the basis for a team’s SLE?” โ†’ the scatterplot.
  • “The 85th-percentile line is at 9 days โ€” what does that mean?” โ†’ ~85% of items finish in โ‰ค 9 days.
  • Trap: confusing it with the aging chart โ€” the scatterplot is finished items; the aging chart is in-progress items.

Cumulative Flow Diagram (CFD)

What it shows. Stacked cumulative bands over time โ€” one band per workflow state. Each line is a running count of items that have entered that state. The only chart showing all three of WIP, approximate Cycle Time, and Throughput at once.

The three readings (memorise this mapping).

CFD featureMetric
Vertical band height at a dateWIP in that state
Horizontal distance between arrival and departure linesApproximate Cycle Time
Slope of the “Done” departure lineThroughput (steeper = more finishing per period)

Healthy vs unhealthy.

  • Healthy: bands roughly parallel, steady departure slope, stable widths.
  • Bottleneck: an in-progress band widens over time while the Done slope flattens โ†’ growing queue.
  • Stalled flow: flat departure line = nothing is finishing.
  • Scope growth: top line climbs steeply = work being added faster than done.

Worked example. Over two weeks the In-Progress band steadily widens while the Done line flattens โ†’ WIP is piling up and throughput is dropping: a bottleneck. Fix: stop starting and swarm, not start more work.

How questions come.

  • “On a CFD, Throughput is read from ___” โ†’ the slope of the departure line.
  • “A steadily widening band indicates ___” โ†’ a growing queue / bottleneck.
  • Trap: keep height = WIP, distance = cycle time, slope = throughput straight.

Throughput Run Chart

Axes. x = time period (day/week/Sprint); y = number of items finished in that period.

What it shows. The delivery rate over time. Even bars = predictable delivery. Erratic bars = less predictable, requiring wider forecast ranges.

Used for. Capacity input at Sprint Planning; the data source for Monte Carlo forecasts; spotting delivery-rate trends.

How questions come.

  • “Which metric/chart informs how much the team can take on?” โ†’ Throughput.
  • “Is this velocity?” โ†’ No โ€” throughput counts items finished, no size compensation.
  • Trap: a Sprint burndown or velocity chart is not a flow chart.

Aging Work-in-Progress Chart

What it shows. A snapshot of today โ€” every in-progress item in its current workflow column, with y-axis = its age (days since started). SLE percentile lines are overlaid.

How to read it. Items at or above the SLE line are at risk of being late. Items sitting a long time in early columns are stalled. Unlike the scatterplot (history), this is a live, forward-looking picture of work you can still act on.

Worked example. An item is 6 days old against an 8-day SLE and still only in “In Progress” โ†’ swarm it now, before it breaches. An item the same age but already in “Review” may be fine.

Used for. The team’s active-management tool, especially in the Daily Scrum โ€” deciding what to finish first and intervening before an SLE breach.

How questions come.

  • “Which chart/metric helps the team decide what to focus on in the Daily Scrum?” โ†’ aging chart / Work Item Age vs SLE.
  • Trap: choosing Cycle Time (only known after finishing โ€” too late) instead of Work Item Age.

F7. Service Level Expectation (SLE)

What it is. A forecast of how long a single item should take, expressed with a probability. It has two parts: a period of elapsed time + a probability (e.g., “85% of items finish within 8 days”).

Mechanics. Derived from historical cycle time โ€” typically a percentile on the scatterplot (85th is a common starting point). Used to actively manage flow: compare a live item’s Work Item Age to the SLE to spot risk. The SLE should be displayed for transparency.

Key rule. Higher confidence โ‡’ longer time. An 85% SLE quotes a longer period than a 50% SLE. An SLE is probabilistic โ€” never an exact-date guarantee.

Misconception to avoid. “SLE = a deadline / SLA you must hit.” It’s an expectation/forecast with a confidence level.

Worked example. The team’s scatterplot shows 85% of items finishing within 8 days โ†’ SLE is “85% within 8 days.” A manager asks them to “promise day 8 exactly.” That misuses the SLE โ€” it expresses an 85% likelihood; pushing to ~95% confidence would mean quoting a longer time (e.g. 13 days).

How questions come.

  • “An SLE consists ofโ€ฆ” โ†’ a period of elapsed time + a probability.
  • “Team promises an exact date from an 85% SLE.” โ†’ wrong; an SLE is probabilistic.
  • “An 85% SLE vs a 50% SLE โ€” which quotes a longer time?” โ†’ the 85% one.

F8. Forecasting & Monte Carlo

What a forecast is. A probabilistic projection of a future outcome based on historical flow data โ€” explicitly not a commitment.

Decision rule โ€” pick the right basis.

QuestionBasis
When will this in-progress item finish?Work Item Age against the SLE / cycle-time history
How many items by date X? / When will N items be done?Throughput history, ideally via Monte Carlo

Monte Carlo mechanics. Rather than a single average, it randomly samples historical throughput across many simulated runs, producing a probability distribution โ€” e.g., “85% chance of finishing the 20 items within 6 weeks.” It surfaces uncertainty honestly instead of hiding it behind a false single number.

Worked example. Asked “when will these 20 items be done?”, the team runs Monte Carlo on recent throughput and reports a range: 50% by week 4, 85% by week 6. They present it as a forecast, not a promise โ€” and would use Work Item Age instead if the question were about a single already-started item.

How questions come.

  • “Forecast when this started item finishes.” โ†’ Work Item Age / SLE.
  • “Forecast how many items next Sprint / by a date.” โ†’ Throughput (Monte Carlo).
  • “Is a forecast a commitment?” โ†’ No โ€” probabilistic projection.

Next: Part G โ€” Kanban in the Scrum Events โ€” how flow metrics slot into each event without changing Scrum’s structure.