H1. The Trap Taxonomy

Almost every wrong answer on the PSK-I belongs to one of eight families. When an option feels wrong but you can’t say why, check it against this list.

Trap 1: Structure-Change Trap

Pattern. Adds a role/event/artifact, drops the Sprint, or creates a “Kanban variant” of a Scrum event. Signature. “Kanban Master,” “Flow meeting,” “flow artifact,” “replace the Sprint with continuous flow.” Rule. Kanban adds four practices, not structure. Violates “Scrum is still Scrum.”

Trap 2: Push / Utilisation Trap

Pattern. “Keep everyone busy,” “raise WIP to raise throughput,” “push work forward.” Rule. Contradicts pull and flow. Raising WIP lengthens cycle time without improving throughput.

Trap 3: Commitment-as-Guarantee Trap

Pattern. Treats a forecast, SLE, or projection as an exact date or firm promise. Rule. Forecasts and SLEs are probabilistic. “We’ll be done by Thursday” from an 85% SLE is false precision.

Trap 4: Target Trap

Pattern. Calls a WIP limit a goal, target, or minimum. Rule. A WIP limit is a maximum. Reaching it is a signal to finish, not a score to hit.

Trap 5: Authority Trap

Pattern. SM or manager assigns tasks, sets WIP limits, or owns the Definition of Workflow. Rule. The Scrum Team self-manages and owns the DoW. The SM enables โ€” does not direct.

Trap 6: Replace Trap

Pattern. “The DoW replaces the DoD,” “Kanban replaces Scrum events,” “Kanban supersedes the Scrum Guide.” Rule. Kanban complements. The Scrum Guide applies in full. The DoW extends the DoD, never replaces it.

Trap 7: Newer-is-Righter Trap

Pattern. Expansion-Pack concepts presented as exam truth: “Definition of Outcome Done,” “Supporters,” “Stakeholders” as a formal accountability, Cynefin. Rule. The exam tests the 2020 Scrum Guide + Kanban Guide for Scrum Teams, not the Expansion Pack. Anything outside those sources is a distractor.

Trap 8: Wrong-Metric Trap

Pattern. Using Cycle Time to judge in-progress risk, or treating velocity as a flow metric. Rule. Cycle Time is a lagging indicator โ€” only known after finishing. For in-flight risk, use Work Item Age. Velocity is not one of the four flow metrics.


H2. Calculation Patterns (Little’s Law)

Keep these three rules in memory. When the exam gives you a numbers question, identify which two variables are known and apply the right one.

GivenSolve forFormula
WIP + ThroughputCycle TimeWIP รท Throughput
WIP + Cycle TimeThroughputWIP รท Cycle Time
Cycle Time + ThroughputWIPCycle Time ร— Throughput
Item count + ThroughputTime to completeCount รท Throughput
Throughput + time periodsForecast itemsThroughput ร— Periods (a forecast, not a promise)

Quick-check drill (run through these before the exam):

ScenarioAnswer
WIP 12, Throughput 3/day โ†’ Cycle Time4 days
WIP 10, Throughput 2/day โ†’ Cycle Time5 days
18 items, Throughput 6/week โ†’ time3 weeks
Cycle Time 4 days, Throughput 3/day โ†’ WIP12
WIP 15, Cycle Time 5 days โ†’ Throughput3/day

H3. Tie-Breakers (when two options both look plausible)

Use these in order when stuck:

  1. Keep Scrum intact. Between two structurally different options, choose the one that doesn’t add or remove a Scrum element.
  2. Pull over push. Finishing over starting. Flow over utilisation.
  3. Probabilistic over guaranteed. A forecast/SLE is never a promise.
  4. Team over manager. Self-management over control. The Scrum Team owns its own process.
  5. On True/False, an absolute can be True. If an option faithfully restates a rule from the Scrum Guide or Kanban Guide, it can be True even if it sounds absolute. Absolutes are not automatically wrong.
  6. Source hierarchy. 2020 Scrum Guide + Kanban Guide for Scrum Teams > blogs > courseware > dumps. When in doubt, ask: “Is this in the guide?”

H4. Exam-Day Tactics

Time budget. 45 questions in 60 minutes = ~80 seconds per question. That’s tighter than it sounds. Flag and move โ€” never leave a blank (there’s no penalty for guessing under a percentage bar; an unanswered question is a guaranteed zero).

Multiple-answer questions. Select exactly the number indicated โ€” no more, no less. Partial selections are marked wrong. When the question says “select 2,” there are exactly 2 correct answers.

Reading order. Read the question first, then scan the scenario stem for only the relevant facts. Scenarios often include irrelevant details designed to anchor you to a wrong answer.

Before booking. Aim to score 95%+ repeatedly on the Scrum with Kanban Open (free at scrum.org). Keep an error log that maps each miss to the guide section. If you’re missing the same category of question more than once, that’s the section to revisit, not the ones you’re already getting right.

The single fastest mental check for any answer. Ask: “Does this option keep Scrum intact and improve flow without adding structure?” If yes, it’s almost certainly right. If it adds a role, drops an event, guarantees an outcome, or keeps people busy at the expense of finishing work โ€” it’s almost certainly wrong.


Series recap

PartCore idea
A โ€” Scrum FoundationsEmpiricism + lean thinking; TIA chain; five values; immutable-but-incomplete framework
B โ€” The Scrum TeamOne cohesive unit; three accountabilities; self-management; PO is one person
C โ€” The EventsSprint as container; know the timeboxes; only PO cancels Sprint; Review adapts the backlog
D โ€” Artifacts & CommitmentsMatch artifact to commitment; DoD can only get stricter; PO decides release
E โ€” Kanban CoreStrategy, not a board; four practices only; DoW owned by team; WIP limit is a maximum
F โ€” Flow MetricsFour metrics only; Cycle Time vs Work Item Age; four charts; SLE is probabilistic; Little’s Law
G โ€” Kanban in EventsNo new events; throughput at Planning; WIP+Age at Daily; CFD at Review; DoW at Retro
H โ€” Exam PatternsEight trap families; Little’s Law shortcuts; tie-breakers; 80 seconds/question

Good luck on the assessment. The Scrum with Kanban Open is your best free calibration tool โ€” use it until the score is consistent.


Back to the start: PSK-I Exam Prep: Complete Study Guide Overview